why dont u divide the work by package/ area and make a sub directory, so ..it wouldnt be duplicate when u update.

Member for

21 years 6 months

it doesn’t matter, as long as someone else is not trying to change the same thing as you, or working in the same section as you. P3e and P3 schedule a database only and your screen will show a reflection of what is on the database. I have had 10 planners working on one database and never had a problem except for speed

Member for

20 years 4 months

Does P3e have a check in/check out option? I would do that so that only one person can write to the file at a time.