Histograms for Different Resources

Member for

19 years 9 months

i have got that done now.

many thanks

Member for

19 years 9 months

many thanks for your reply,

but there is no filter selection option under resource usage profile GRAPH OPtion, I am using Projection Management Software (P3e).

Member for

22 years 3 months

You need to right click on the graph and select ’Resource Usage Profile Options’, where you need to set some filters and choose a colour for each filter output.



Cheers



Kevin

Member for

19 years 9 months

but when you checked on staked histograme every thing disappeared.

Member for

22 years 3 months

You could try using the Stacked Histogram, however a problem using this is that it shows individual resource usage based on the currently filtered activities rather than the selected activities.