Look under Tools / Schedule / Options / General. There you will find the option, "Calculate start-to-start lag from:". Your options are early start & actual start. Good luck!
Member for
20 years 8 months
Member for20 years8 months
Submitted by Sukumaran Suba… on Wed, 2006-06-14 22:47
Member for
19 years 5 monthsRE: using actual dates in relationships
thank you all..
regards..
Member for
22 years 10 monthsRE: using actual dates in relationships
Look under Tools / Schedule / Options / General. There you will find the option, "Calculate start-to-start lag from:". Your options are early start & actual start. Good luck!
Member for
20 years 8 monthsRE: using actual dates in relationships
Actual means it is already happen and past. Now the activities are considered as As-Built.
You can add or reduce the lag to current and future activities only, i.e. after the data date.
Regards.