% of progress (Mhrs versus EVA)

Member for

19 years 3 months

Dear Friend,

Difference encountering simply because per cost is different for both and %complete is also both..if u consider invidual cases u will get the same %complete(that is activity 1 its self 100% abd activity 2 100%). But if u going as cumulative natuaraly the problem arises.

Member for

19 years 5 months

Yes - you can use both methodes.



If the management can’t see the difference in

% of manhours and

% $ budget

the should look for a job in accounting,

where they can consentrate on the money.



To help them see this you should clearify it in your setup.

e.g.

23.63% of manhour budget

20,78% of manhour-costs budget



or



you can switch to average manour costs and loose control over the costs.

But the % will at least be the same.....



Svein