The PRIM quoted does not seem to be right - but not to worry
What I was looking for was where EPS Activity codes are deleted for no apparent reason. The reason that I since found is that I used Check Project Integrity
There is a glitch in P3e when EPS level Activity code assignments are removed by Check Project Integrity prim32313.
So the moral is do not use Check Project Integrity
Now to remap the Activity codes - oh well. Thank god for backups.
Member for
21 years
Member for21 years1 month
Submitted by Amir Dadbakhsh on Tue, 2006-05-23 07:41
This is a known defect with Primavera 5 with the combination of SQL Server, Paste Project, and User defined Activity fields. See prim30231 in the Support knowledgebase.
You have two workarounds that will resolve this.
1. When copying projects, organize the projects screen by something other than EPS. Problem is only when pasting and you are organized by EPS. Or
2. Add the following setting in the PM.INI file in the section [Options]
UseSPToPasteProject=0
Solution 2 will force the program to not use a stored procedure used when copying. Problem is with the stored procedure.
Regards,
Bill
Member for
21 years
Member for21 years1 month
Submitted by Amir Dadbakhsh on Mon, 2006-05-22 09:10
Member for
20 years 5 monthsRE: UDF - Loosing data!!!
Thanks for this thread.
The PRIM quoted does not seem to be right - but not to worry
What I was looking for was where EPS Activity codes are deleted for no apparent reason. The reason that I since found is that I used Check Project Integrity
There is a glitch in P3e when EPS level Activity code assignments are removed by Check Project Integrity prim32313.
So the moral is do not use Check Project Integrity
Now to remap the Activity codes - oh well. Thank god for backups.
Member for
21 yearsRE: UDF - Loosing data!!!
Dear Bill
I changed PM.INI and it worked (I copied a project without any problem).
Thanks a lot
Amir
Member for
20 years 10 monthsRE: UDF - Loosing data!!!
Amir,
This is a known defect with Primavera 5 with the combination of SQL Server, Paste Project, and User defined Activity fields. See prim30231 in the Support knowledgebase.
You have two workarounds that will resolve this.
1. When copying projects, organize the projects screen by something other than EPS. Problem is only when pasting and you are organized by EPS. Or
2. Add the following setting in the PM.INI file in the section [Options]
UseSPToPasteProject=0
Solution 2 will force the program to not use a stored procedure used when copying. Problem is with the stored procedure.
Regards,
Bill
Member for
21 yearsRE: UDF - Loosing data!!!
Dear Bill,
A)I mean "User Defined Fields" and "Activity" Section (Sorry I wrote my previous message wrong and I correct it here!).
B)First I prepared mentioned plan in primavera 4.1 (Interbase) then after while I have brought it (convert it) to primavera 5.0 (SQL database).
Thanks
Amir
Member for
20 years 10 monthsRE: UDF - Loosing data!!!
Amir,
Are these activity codes or activity UDFs ? The subject reads UDF, but the body of the message indicates codes.
Also are you using an Oracle or SQL Server / MSDE database.
Regards,