achievable schedule???

Member for

20 years 6 months

to use informaker, you need install ODBC driver and config data source,then you can open your project in informaker for reporting.



there are lots of threads about link MS-Access with P3,

MS-access is more easy and powerful than informaker.

In most case, export to excel is enough, if this does not work, try Access. No need to learn informaker.

Member for

19 years 11 months

hi

1) can u one tell me how infomakes useful 2 us?

i don wats it? thnk its link???m confused


Member for

20 years 6 months

first set the start date of the project,

then assign duration for each activity

then link all acvities with relationship.

P3 will caculate ES,EF for you.



If the duration and relationship is reasonable based on your resource availability, then the schedule is achievable.