Steps - P5

Member for

20 years

Thanks Mario.

Member for

20 years

Thanks for your response David.



I normally use STEPS on my schedulles.



But what i would like to know is:



Is there advantages for STEPS on P5 release?



Best regards.



Marcio Eduardo.

Planning & Control - P53

Rio de Janeiro - Brazil

Member for

23 years 11 months

Steps are particularly useful for small activities that do not need to be done in sequence. Each step can be weighted which gives an accurate measure of work completed. A typical example is production of a drawing package





Overall Drawinng 10%

Detailed Drawings 60%

Bill of Materials 5%

Test Specifications 25%