Oracle Primavera - PM6 Member for 20 years 1 month Member for 20 years 1 month Submitted by Emma Seaton on Fri, 2006-04-28 12:35 Permalink RE: Pv5 Earned Value field is blank No need to answer - Ive found it, as luck would have it AFTER I posted the question - its the activity % complete which is used to calculate the Performance % Complete!!! Course I should have known already!! ;o) Log in or register to post comments
Member for 20 years 1 month Member for 20 years 1 month Submitted by Emma Seaton on Fri, 2006-04-28 12:35 Permalink RE: Pv5 Earned Value field is blank No need to answer - Ive found it, as luck would have it AFTER I posted the question - its the activity % complete which is used to calculate the Performance % Complete!!! Course I should have known already!! ;o)
Member for
20 years 1 monthRE: Pv5 Earned Value field is blank
No need to answer - Ive found it, as luck would have it AFTER I posted the question - its the activity % complete which is used to calculate the Performance % Complete!!! Course I should have known already!! ;o)