Tasks showing up as critical that are not

Member for

19 years 6 months

Alexandre,

Thanks for your reply. In the interim time period between my original post and now.....I realized that when we converted the file from P3, some resource calendars came over as well. These calendars were driving activities critcal. So thanks again for the reply!

Member for

22 years 9 months

Hello,

it is a difficult question to answer without having the file on screen.

do you have resources being assigned on tasks and presumably THIS task? what about calendars?

where is the task situated in the project duration?

If you want to send me your files, just give me a Personal Message.

Alexandre