Sounds like no then. It’s not isolation that I’m after, but accurate worker-hour calculation together with load levelling and over-allocation notification. thanks for the reply.



andrew

Member for

24 years 6 months

Andrew



Your options are Work or Material.



You can tag resources, say with a Group, to isolate if it is equipment or people, this may assist.