Yes - P3e do have CDI (what they call now is user define field
Yes it can calculate base on a activities level where the basic calculation is allow (No global change needed) (ONLY in Version 5)
No you cannot just adding the % together. because each summary level is different. As a result, it cannot work out CPI SPI at a summary by using CDI/UDF
Therefore, the two options are
1 use the standard EV calculated function in P3e
2 use the UDF and export to excel to calculate EV
HTH
Alex
Member for
20 years 7 months
Member for20 years8 months
Submitted by Hazel Mendez on Wed, 2006-05-17 23:51
Is it possible to define weight value code on "custom data items" and add weight value for each activities and show percent complete based on this weight value? Im not sure if "custom data item" function is available in P3 e/c.
Your reply to this matter will be highly appreciated. Thank you.
hazel
Member for
21 years 6 months
Member for21 years6 months
Submitted by Brian Cameron on Tue, 2006-02-14 18:33
Im not sure if your "project" is actually a program (a collection of projects) in Primavera. If so, then Ill just tackle a WBS.
Lets assume that a WBS is actually a Work Package that is contracted out, and therefore is a project in itself.
Lets also assume that you measure progress for this WBS by Physical Percent Complete.
The reason for these assumptions is that if youre inquiring about the total percent complete of a group of projects, each using different bases of progress measurements (duration, physical, etc.) then thered be a lot lot more discussion on how to valuate these different activities.
So going back to the Work Package, if actities are costed (via using resources that have unit prices OR by loading expenses as reflected in the contract document), and you set the measurement of all activities in the WBS to Physical Percent Complete, then by displaying Activity Percent Complete in the Column, Primavera can give you a Total Percent Complete for that specific WBS.
This is because it is comparing apples to apples. It uses Earned Value to come up with your WBS Percent Complete.
Now, if you have another Work Package that is duration-based for progress measurement, Primavera will simply use the total of that WBS as the total number of work periods used as the basis for your Activity Percent Complete, and consequently for the WBS Percent Complete.
However: Please check also the settings for WBS earned value.
The problem lies in asking Primavera what is the total percent complete of the whole program (if you used WBS to contain each project). How does Primavera weigh a duration-based activity with no costs (resource or expenses) with a physical-based activity (which are costed?).
Also, for a long-term program where some Work Packages are still being planned (no budget), while others are already being executed and others are already closed out: How will Primavera (or any other software, for that matter) give you a "Project" percent complete.
This is the reason i focused on a single Work Package (WBS Node).
Hope this helps.
Best regards,
Jorge
Member for
20 years 8 months
Member for20 years8 months
Submitted by Larry Swindall on Mon, 2006-02-13 09:50
If all you want is a project percent complete, then set up a hammock representing all of your activities. This will then show the the overall project percent complete.
Member for
21 years 6 months
Member for21 years6 months
Submitted by Brian Cameron on Wed, 2006-02-08 20:22
The solution was a combination of showing the duration % column, progressing the schedule and having the totals selected in the group and sort.
When all of those were applied the information was visible.
This was on a new schedule and I hadnt scheduled it after entering the first progress collected(asked not to by others!!), so things werent behaving as I expected.
Please check whether you resource have at least $1 attached to it. If it does than you can use EVMS (Earn Value) / Physical % to indicate the project completion.
BTW do you update individual activity %??
Alex
Member for
21 years 6 months
Member for21 years6 months
Submitted by Brian Cameron on Wed, 2006-02-08 17:03
WOW, such a big topic in P3e, Percent Complete and how to roll it up. I run a half day workshop for expert users on the subject. In summary:
1) if you do not use resources, use "Duration percent complete"
2) If you use resources, and they are all priced (if you do not use resource unit prices, set them all to 1.00) then use "performance per cent complete"
You need to show the appropriate column to get a summary percent complete. The Duration % Complete, Units % Complete and Cost % Complete will usually show different values.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
Member for
22 years 8 monthsRE: Primavera V4.1 - Show % in Total
Hazel
The answer is yes and no
Yes - P3e do have CDI (what they call now is user define field
Yes it can calculate base on a activities level where the basic calculation is allow (No global change needed) (ONLY in Version 5)
No you cannot just adding the % together. because each summary level is different. As a result, it cannot work out CPI SPI at a summary by using CDI/UDF
Therefore, the two options are
1 use the standard EV calculated function in P3e
2 use the UDF and export to excel to calculate EV
HTH
Alex
Member for
20 years 7 monthsRE: Primavera V4.1 - Show % in Total
Hello,
Is it possible to define weight value code on "custom data items" and add weight value for each activities and show percent complete based on this weight value? Im not sure if "custom data item" function is available in P3 e/c.
Your reply to this matter will be highly appreciated. Thank you.
hazel
Member for
21 years 6 monthsRE: Primavera V4.1 - Show % in Total
Thanks Guys for your responses.
Ill try out a few things you have mentioned.
The original post was for a project, but it is part of a program, so I can use you suggestions for both scenarios.
Regards
Brian.
Member for
22 years 4 monthsRE: Primavera V4.1 - Show % in Total
Hi Brian,
Im not sure if your "project" is actually a program (a collection of projects) in Primavera. If so, then Ill just tackle a WBS.
Lets assume that a WBS is actually a Work Package that is contracted out, and therefore is a project in itself.
Lets also assume that you measure progress for this WBS by Physical Percent Complete.
The reason for these assumptions is that if youre inquiring about the total percent complete of a group of projects, each using different bases of progress measurements (duration, physical, etc.) then thered be a lot lot more discussion on how to valuate these different activities.
So going back to the Work Package, if actities are costed (via using resources that have unit prices OR by loading expenses as reflected in the contract document), and you set the measurement of all activities in the WBS to Physical Percent Complete, then by displaying Activity Percent Complete in the Column, Primavera can give you a Total Percent Complete for that specific WBS.
This is because it is comparing apples to apples. It uses Earned Value to come up with your WBS Percent Complete.
Now, if you have another Work Package that is duration-based for progress measurement, Primavera will simply use the total of that WBS as the total number of work periods used as the basis for your Activity Percent Complete, and consequently for the WBS Percent Complete.
However: Please check also the settings for WBS earned value.
The problem lies in asking Primavera what is the total percent complete of the whole program (if you used WBS to contain each project). How does Primavera weigh a duration-based activity with no costs (resource or expenses) with a physical-based activity (which are costed?).
Also, for a long-term program where some Work Packages are still being planned (no budget), while others are already being executed and others are already closed out: How will Primavera (or any other software, for that matter) give you a "Project" percent complete.
This is the reason i focused on a single Work Package (WBS Node).
Hope this helps.
Best regards,
Jorge
Member for
20 years 8 monthsRE: Primavera V4.1 - Show % in Total
If all you want is a project percent complete, then set up a hammock representing all of your activities. This will then show the the overall project percent complete.
Member for
21 years 6 monthsRE: Primavera V4.1 - Show % in Total
Alex
The solution was a combination of showing the duration % column, progressing the schedule and having the totals selected in the group and sort.
When all of those were applied the information was visible.
This was on a new schedule and I hadnt scheduled it after entering the first progress collected(asked not to by others!!), so things werent behaving as I expected.
Thanks for your reply.
Brian.
Member for
22 years 8 monthsRE: Primavera V4.1 - Show % in Total
Brain
Please check whether you resource have at least $1 attached to it. If it does than you can use EVMS (Earn Value) / Physical % to indicate the project completion.
BTW do you update individual activity %??
Alex
Member for
21 years 6 monthsRE: Primavera V4.1 - Show % in Total
Hi Dave
I tried Paul Harriss ideas and I didnt get what I wanted, probably because of a few things I have not set up correctly!
What I have set up doesnt fit your two solutions.
The best bet is I give you an idea of what I have.
The project defaults are set as fixed duration and units, percent complete type physical, and resource dependent.
The general information about the activities are that they are resource dependent, fixed duration and units and physical percent complete type.
Resources are set at 8hr/dy and are unpriced, because time collection and finance is controlled through another system.
Basically just a activities in a WBS layout linked together with durations, hours and resources.
Any ideas ?
Regards
Brian.
Member for
21 yearsRE: Primavera V4.1 - Show % in Total
WOW, such a big topic in P3e, Percent Complete and how to roll it up. I run a half day workshop for expert users on the subject. In summary:
1) if you do not use resources, use "Duration percent complete"
2) If you use resources, and they are all priced (if you do not use resource unit prices, set them all to 1.00) then use "performance per cent complete"
Member for
24 years 7 monthsRE: Primavera V4.1 - Show % in Total
Brian
You need to show the appropriate column to get a summary percent complete. The Duration % Complete, Units % Complete and Cost % Complete will usually show different values.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au