Cumulative Cash Flow Curve?

Member for

21 years

Dear All;

Here is the solution to my concern:



Tools > Tabular Reports > Cost > Tabular...



Add or Modify one of the existing report in Tabular Cost Reports. (I prefer to modify the existing one.)

On the Timescale Window,

select Schedule 1: Current Early,

select Schedule 2: Current Late,

select Schedule 3: None

and export to data file in WK1.

Run the report.

Then we have the WK1 Format of data.Copy it to excel and prepare what ever report you like in excel.

Member for

21 years

Syure I have an original program. However I dont think that it is related with the originality of program.

Regards

Member for

19 years 11 months

Dear David ***Moses



Thank you for your question,



But infact , to create that report you must has a orginal program ((i main Primavera project planner)), sothat you should told me if you have that orginal version



with best wishes



Good new year





Engineer:Yousif .Ayal

Iraq