Changing the Projects Time Period

Member for

21 years 6 months

Thank You very much for your guidance. I finally worked out what you meant.

Member for

21 years 6 months

I don’t have that option.

If I click on PROJECT-



Activities

Resource Assignments

WBS

______________

Baseline

Expenses

Work Products and Documents

______________



Threshold

Issues

Risks

_______________

Set Default Project

Member for

20 years

Ok Mario,



Go on PROJECT view > DATES > and change MUST FINISH BY.



Hope it can help u.



Best regards,



Marcio Eduardo.

Rio de Janeiro - Brazil.

Member for

21 years 6 months

My existing project has a project start date of April ’05 and a project finish date of March’06. I have now added in activities for April ’06. These activities are showing critical. My guess is that this is due to the project finish date.



I figured if I could change the project finish date it would sort out the activities that are showing critical.

Member for

20 years

Sorry Mario,



I cant understand what are u trying to do.



Do u have a timeschedule with 1 year durarion and whant to become it 2 years durarion, ok??



Does this timeschedule has any progress? Or it didnt start yet?



Probably u will have to change activity durations to achive 2 years, or detail more WBS inserting more activities etc.



My first impression is that u are replanning your project. Is that ok??



Regards.



Marcio Eduardo.