I suggest you have to test run it first for P3e-P3-P3e
I cannot see a great problem if your import and export setup is correct. Meaning the updating code, resource code, activity code, calenda, WBS.
P3e - P3 should be simple All information should be there
P3 - P3e require a bit of co-ordination between you and your sub becasue P3 only have limited activity and project code (and limited lenght as well) you have to do some global change to convert it to your master schedule
Regards
Alex
Member for
23 years
Member for23 years
Submitted by Steven Oliver on Wed, 2005-11-09 09:43
Member for
22 years 8 monthsRE: P3 to P3e convert.
I suggest you have to test run it first for P3e-P3-P3e
I cannot see a great problem if your import and export setup is correct. Meaning the updating code, resource code, activity code, calenda, WBS.
P3e - P3 should be simple All information should be there
P3 - P3e require a bit of co-ordination between you and your sub becasue P3 only have limited activity and project code (and limited lenght as well) you have to do some global change to convert it to your master schedule
Regards
Alex
Member for
23 yearsRE: P3 to P3e convert.
Basically, dont go there.
P3e has so many things which P3 doesnt.
You will spend massive amounts of time checking the results.