P3 to P3e convert.

Member for

22 years 8 months

I suggest you have to test run it first for P3e-P3-P3e



I cannot see a great problem if your import and export setup is correct. Meaning the updating code, resource code, activity code, calenda, WBS.



P3e - P3 should be simple All information should be there

P3 - P3e require a bit of co-ordination between you and your sub becasue P3 only have limited activity and project code (and limited lenght as well) you have to do some global change to convert it to your master schedule

Regards

Alex

Member for

23 years

Basically, dont go there.



P3e has so many things which P3 doesnt.



You will spend massive amounts of time checking the results.