The easiest way to assign one or multiple resources to multiple activities is to use the " Assign Resources" dialog which is accessed by the Resources Button on the Command bar. It will assign resources to selected or highlighted activities. Combine with an activity filter if the assignment needs to meet a selection criteria.
Member for
20 years 1 monthRE: How to add common resources to P3e/c by using Global Ch
Bill,
Thank you for the support. I did follow your suggestion and it works.
Member for
20 years 10 monthsRE: How to add common resources to P3e/c by using Global Ch
Ruel,
The easiest way to assign one or multiple resources to multiple activities is to use the " Assign Resources" dialog which is accessed by the Resources Button on the Command bar. It will assign resources to selected or highlighted activities. Combine with an activity filter if the assignment needs to meet a selection criteria.
Regards,
Bill