Primavera Project Planner - P3 Member for 20 years 5 months Member for 20 years 5 months Submitted by Raja Izat Raja… on Sat, 2005-10-01 14:18 Permalink RE: planned cost U can insert column Schedule variance (BCWS-BCWP). or u can ceate another using global change, as u like. for reference "how to use global change" u can go to P3 sample or go to old post thread in PP. further question ...just reply. Log in or register to post comments
Member for 20 years 5 months Member for 20 years 5 months Submitted by Raja Izat Raja… on Sat, 2005-10-01 14:18 Permalink RE: planned cost U can insert column Schedule variance (BCWS-BCWP). or u can ceate another using global change, as u like. for reference "how to use global change" u can go to P3 sample or go to old post thread in PP. further question ...just reply.
Member for
20 years 5 monthsRE: planned cost
U can insert column Schedule variance (BCWS-BCWP). or u can ceate another using global change, as u like. for reference "how to use global change" u can go to P3 sample or go to old post thread in PP.
further question ...just reply.