The project Im on we dont have money uploaded and to be able to show both mandays and manhours I assign a cost of 10 for each manday. Earned Value can be calculated for both, you just specify whether its resource or cost based.
Hope this helps.
Alex
Member for
20 years 8 months
Member for20 years8 months
Submitted by Sukumaran Suba… on Tue, 2005-09-20 05:20
a) check what is the allocated working hours per day.
b) make a copy of the current file and change the planning unit to hour.
c) then do all the necessary changes using global change.
If you just change the duration to manhours than I dont think there is any significant effect because you are merely converting the duration from 1 day to 24 hours, which is generally the same. That means your EV is still the same as before.
Regards.
Member for
20 years 5 months
Member for20 years5 months
Submitted by Raja Izat Raja… on Tue, 2005-09-20 04:33
Nothing will effect EV, We just mutiply Mandays to Manhours in GlobalChange and generate in report writer but if we change the origin Data from Mandays to Manhours of cause it will totaly change the EV. It will create more works to be done.
Member for
23 years
Member for23 years
Submitted by Steven Oliver on Tue, 2005-09-20 04:12
You can try to copy the project (Tools, Project Utilities, Copy) and then change the planning units there. You can then make the changes using Global Change
Member for
20 years 5 months
Member for20 years5 months
Submitted by Raja Izat Raja… on Fri, 2005-09-16 12:33
Member for
21 years 2 monthsRE: P3 schedule from mandays to manhours
Hi,
The project Im on we dont have money uploaded and to be able to show both mandays and manhours I assign a cost of 10 for each manday. Earned Value can be calculated for both, you just specify whether its resource or cost based.
Hope this helps.
Alex
Member for
20 years 8 monthsRE: P3 schedule from mandays to manhours
Jeffrey,
If you want to change from mandays to manhours:
a) check what is the allocated working hours per day.
b) make a copy of the current file and change the planning unit to hour.
c) then do all the necessary changes using global change.
If you just change the duration to manhours than I dont think there is any significant effect because you are merely converting the duration from 1 day to 24 hours, which is generally the same. That means your EV is still the same as before.
Regards.
Member for
20 years 5 monthsRE: P3 schedule from mandays to manhours
Hi Steve,
Nothing will effect EV, We just mutiply Mandays to Manhours in GlobalChange and generate in report writer but if we change the origin Data from Mandays to Manhours of cause it will totaly change the EV. It will create more works to be done.
Member for
23 yearsRE: P3 schedule from mandays to manhours
What effect do you think this will have on the way Earned Value is calculated ?
Member for
20 years 2 monthsRE: P3 schedule from mandays to manhours
Hi Jeff,
You can try to copy the project (Tools, Project Utilities, Copy) and then change the planning units there. You can then make the changes using Global Change
Member for
20 years 5 monthsRE: P3 schedule from mandays to manhours
Hi Jeff,
I suggest u use global change.