My apologies. Being only a humble user of P3 Ver 3.1 I forgot I was in a P3e thread. Actually I have my upgrade to P3e but due to current project pressures have not loaded it yet. I guess you will be getting queries from me once I start delving into its workings in the near future.
Paul
Member for
20 years 10 months
Member for20 years11 months
Submitted by Bill McMichael on Wed, 2005-09-07 12:11
The spreadsheet field option gives a choice among "Remaining Units", "Actual Units" and "Budgeted Units" only. it does not give option of baseline unit. Can you explain me how to add baseline units as an additional option?
Member for
23 years
Member for23 years
Submitted by Steven Oliver on Fri, 2005-09-02 03:53
You cant do it with the WYSIWYG. Try Resource/Cost Graphics. Go to Tools, Graphics Reports, Resource and Cost. In the content section you can select from Current schedule, Target 1 or Target 2.
Good Luck
Paul Silver
Member for
20 years 8 months
Member for20 years8 months
Submitted by Bijaya Bajracharya on Fri, 2005-08-26 09:00
The profile thus generaged are always from the current programme. I want to generate a profile which shows both baseline and current information. Is there a way to do it?
Member for
21 years 1 monthRE: Budgeted Quantity Profile
Bijaya,
My apologies. Being only a humble user of P3 Ver 3.1 I forgot I was in a P3e thread. Actually I have my upgrade to P3e but due to current project pressures have not loaded it yet. I guess you will be getting queries from me once I start delving into its workings in the near future.
Paul
Member for
20 years 10 monthsRE: Budgeted Quantity Profile
Bijaya,
Take a look at the Activity Usage Profile (View / Show on Bottom Menu) . This will allow you to display current vs baseline.
Regards,
Bill
Member for
20 years 8 monthsRE: Budgeted Quantity Profile
Paul,
It may be different version of programme (I am using P3e/c ver 4.1) but I dont see "Graphical Report" in pull down menu.
Member for
20 years 8 monthsRE: Budgeted Quantity Profile
Steve,
The spreadsheet field option gives a choice among "Remaining Units", "Actual Units" and "Budgeted Units" only. it does not give option of baseline unit. Can you explain me how to add baseline units as an additional option?
Member for
23 yearsRE: Budgeted Quantity Profile
In the Resource View, select the spreadsheet filds option and from the list of available fields choose Baseline Units.
Member for
21 years 1 monthRE: Budgeted Quantity Profile
Bijaya,
You cant do it with the WYSIWYG. Try Resource/Cost Graphics. Go to Tools, Graphics Reports, Resource and Cost. In the content section you can select from Current schedule, Target 1 or Target 2.
Good Luck
Paul Silver
Member for
20 years 8 monthsRE: Budgeted Quantity Profile
This is a further question on this topic.
The profile thus generaged are always from the current programme. I want to generate a profile which shows both baseline and current information. Is there a way to do it?
Member for
22 years 8 monthsRE: Budgeted Quantity Profile
Simple
Firstly you select Resource Usage Profile in the activities View
Secondly you format Resource Usage Profile Option (Right Click in the Graph Area)
Select unit, Tick on Budgeted By Date
Go to the Grahp TAB and tick Calculate Average
And change the divided total by to (0.01) and change the unit of Measure to (%)
Change Time scale to Day month or Week
That way you will resolve the problem not able to display the exact % of time each of your resource.
The reason that your original graph have 1 1 is because the rounding problem by effectively convert the usage to % it become more clear in the Usage %
HTH
Alex
P.S.
I can display a sample if you r interest PM me with your e-mail