To recalculate actual units and costs when % compl changes, there is a project level option to set this. Go to the projects screen, select your project, and choose calculations tab on the bottom form.
There is also a % compl type setting for each activity. For activities where you want the percent complete to be independent of durations, units, and costs, choose "physical". This can be set either in columns or on the activity form -- general tab. When you show Activity % as a column, it will display the appropriate percent complete.
Regards,
Bill
Member for
20 years 6 months
Member for20 years6 months
Submitted by Rashid Iqbal on Fri, 2005-08-05 11:49
Member for
20 years 6 monthsRE: % completion link/unlink RD and Actuals
Thanks Bill, Ill try your suggestions.
Regards
Rashid
Member for
20 years 10 monthsRE: % completion link/unlink RD and Actuals
To recalculate actual units and costs when % compl changes, there is a project level option to set this. Go to the projects screen, select your project, and choose calculations tab on the bottom form.
There is also a % compl type setting for each activity. For activities where you want the percent complete to be independent of durations, units, and costs, choose "physical". This can be set either in columns or on the activity form -- general tab. When you show Activity % as a column, it will display the appropriate percent complete.
Regards,
Bill
Member for
20 years 6 monthsRE: % completion link/unlink RD and Actuals
Thanks for answering though i am trying to figure out the same in P3e/c.
Regards
Rashid Iqbal
Member for
20 years 5 monthsRE: % completion link/unlink RD and Actuals
Hi ,
U just go to tools > option > autocost rules and unlink RD.
regards