Physical % of Completion Vs Schedule % completeion

Member for

20 years 5 months

Hi joseph,

u can play round resource lag, and shift every resources for that activities to 50% elapsed time, so the physical progress will show 0% and Time duration showing 50% or u can put as non working day for that activities for activities for 5 days.

hope this can works...