Microsoft Project Member for 24 years 9 months Member for 24 years 9 months Submitted by Vladimir Liberzon on Tue, 2005-07-19 17:15 Permalink RE: fix cost for all project Create dummy resource with the project daily rate and assign it to the whole project. Max/min resource requirements are not supported by this software. Log in or register to post comments
Member for 24 years 9 months Member for 24 years 9 months Submitted by Vladimir Liberzon on Tue, 2005-07-19 17:15 Permalink RE: fix cost for all project Create dummy resource with the project daily rate and assign it to the whole project. Max/min resource requirements are not supported by this software.
Member for
24 years 9 monthsRE: fix cost for all project
Create dummy resource with the project daily rate and assign it to the whole project.
Max/min resource requirements are not supported by this software.