You would need to create & provide unique activity code for each subcontractor and reflect the same in the program activity id. hence the activity id themselves would help in differentiating the subcontractors when you integrate their programs.
Member for
20 years 6 months
Member for20 years7 months
Submitted by Zhang Haixiang on Tue, 2005-07-12 01:04
you need to develop some procedure for all subcontractor on scheduling,including
name of the project, act ID, codeing structure, resource,how to link tasks from different contractor,level of detail, method of updating...
you need to think about how to update this schedule,you may do this kind of intergation once a week. for a power plant your detail schedule may have more than 50000 tasks. if they are not well organized, you will have big problem when updating them
Member for
21 years 5 monthsRE: INTEGRATION OF SCHEDULES IN P3
You would need to create & provide unique activity code for each subcontractor and reflect the same in the program activity id. hence the activity id themselves would help in differentiating the subcontractors when you integrate their programs.
Member for
20 years 6 monthsRE: INTEGRATION OF SCHEDULES IN P3
Hi,
you need to develop some procedure for all subcontractor on scheduling,including
name of the project, act ID, codeing structure, resource,how to link tasks from different contractor,level of detail, method of updating...
you need to think about how to update this schedule,you may do this kind of intergation once a week. for a power plant your detail schedule may have more than 50000 tasks. if they are not well organized, you will have big problem when updating them