The best way I can think of is export the complete activity list in a excel table and run a VLookup in the activity list that look up the predecessor actual finish date. Run a auto filter to filter your specified conditions.
Export the activity id list
Create a Activity Code
Import the activity ID + A Special Code
Filter the code
I think it is a 5 min job
Cheers
Alex
Member for
20 years 6 months
Member for20 years6 months
Submitted by Jihad Daniel on Wed, 2005-06-29 06:21
Simply check scheduling report which will list the activities completed or started and their predecessors did not start yet...It is not complicated at all...
Member for
22 years 8 monthsRE: Checking predecessor
The best way I can think of is export the complete activity list in a excel table and run a VLookup in the activity list that look up the predecessor actual finish date. Run a auto filter to filter your specified conditions.
Export the activity id list
Create a Activity Code
Import the activity ID + A Special Code
Filter the code
I think it is a 5 min job
Cheers
Alex
Member for
20 years 6 monthsRE: Checking predecessor
Simply check scheduling report which will list the activities completed or started and their predecessors did not start yet...It is not complicated at all...
Regards,
J. Daniel