Checking predecessor

Member for

22 years 8 months

The best way I can think of is export the complete activity list in a excel table and run a VLookup in the activity list that look up the predecessor actual finish date. Run a auto filter to filter your specified conditions.



Export the activity id list



Create a Activity Code



Import the activity ID + A Special Code



Filter the code



I think it is a 5 min job



Cheers



Alex

Member for

20 years 6 months

Simply check scheduling report which will list the activities completed or started and their predecessors did not start yet...It is not complicated at all...



Regards,

J. Daniel