Some activities become open ended while importing xer file in Primavera Risk analysis

S
sanam negi 👤 Member for 13 years 10 months

Hi every one,

 

I imported .xer file into primavera risk analysis, and while doing the schedule check I found out that there are some activities which became open-ended, whereas the activities are not open ended in primavera P6 "view log".

 

Please advise what could be the possible reason or how can i fix this.

 

 

Thanks

sanam

S
sanam negi 👤 Member for 13 years 10 months

Hi david,

 

I tried it but there was some error and i could not find the fix for it. could you please send me the PDF for the error correction or simple steps to do it.

 

Sanam

G
Gary Whitehead 👤 Member for 17 years 3 months

Hi David,

 

I'm very interested to learn how you go about transferring P6 data directly into PRA instead of via an xer.

 

I have some tame IT bods in my office who would probably be willing to give it a go. Could you give us a broad brush description of what is involved?

 

Ta muchly,

 

G

D
David Kelly 👤 Member for 21 years 8 months

Sanam,

 

Start to Finish relationships may not come accross

If you have IT support, the PRA to P6 interface is MUCH better if you can read the P6 data directly into PRA and not through an XER file - but it is tricky to set up, ften needing IT help.

Forum Sponsor

Top Posters

pennyu
0 posts
James Williams
74 posts
jaasland
0 posts
Doron El
3 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts
Siddharth Ranadive
1 posts
Aidar Kurmantayev
0 posts