PRA Cost Roll Up

Hi,

In the Risk Outputs tab of PRA, the P50 cost does not seem to roll up properly. For example the sum of the P50 costs of activities do not always equal the P50 cost of their WBS element, and the sum of the P50 costs of WBS elements does not always equal the P50 cost of their parent WBS element. 

Has anyone else had this issue? 

Any assistance would be greatly appreciated.

Kind regards,

Simon 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts