Imoprting MS project 2010 into Primavera Risk Analysis

Hi all,

 

I have discovered an issue while importing MSP files into PRA.

This arises when the MSP file contains tasks which are already underway i.e started before the import date.

PRA does not carry through this date from project but uses a later date (I think the one the MSP file was created on - also after the tasks which are underway).

 

THe resulr of all this is theat the finish date are very different between the MSP and PRA files.

 

THis might be a silly question but how do I make sure that PRA imports the dates exactly as they are in MSP?

 

Many thanks

 

W