Please help ASAP:P6 XER Imported in to Pertmaster 8 resulted into different dates

Dear Members,

I have created an XER from my Primavera 6.2 schedule. and imported that into Pertmaster. ersult is I have different completion dates on my project as different dates every where in general. I checked the help on Pertmaster and the only thing I could find was that I have to calculate the schedule prior to XER generation (which I had done) and then generate xer. so this didnt solve my problem.

and also I have checked every start and finsih date in primavera and nothing matches whats in pertmaster. but I found primavera start finsih dates in pertmaster in imported early start and finish dates field.

please help me with telling me how to get the same schedule in pertmaster.

 

thanks

Matt

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts