Force Majeure
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
That is not a force majeure!
Samer
Who was responsible for this order? Customer --> reason for claim; you --> prepare for penalty. It will be necessary to check the contract - by an advocat.
Wrong, does it mean you cant use it, or you can use it with modifications or additional work?
I assume you work for an EPC contractor, so your employer most probably is responsible.
But who did expediting, i.e. the suppliers control?
No chance to give an answer without more information.
Regards
Dieter