Weight Factor

Hi All,

i have a project has five WBS and each one of them has a duration and cost, and i need to determine weigth factor for each wbs based on time and cost, is there any method to do that, or there is another method to determine the weight factor?

best,

muataz

M
Mike Testro 👤 Member for 20 years 5 months

Cost is not a reliable method of reporting progress.

Your split of 70 / 30 is too broad an average when in some task the split is 20 / 80 and others 90 / 10.

If you are going to apply this method then you must allocate the correct split to each task.

Also there is a 3rd split of OH&P which is not progress related at all.

M
Mehdi Rashidi Alangeh 👤 Member for 22 years 11 months

Dear moutaz

Hi,

the best way for create weight factors as following items:

1- Cost ( 70 % share)

2- Time ( 30 % share)

Total weight= 70% w.cost+ 30% w.Time

Also you need determain the S.W.U ( Specific Work Units) for in the WBS units.

 

Best Regards

Rashidi

M
moutaz aldeib 👤 Member for 22 years 5 months

Jithin

the case i have is not construction and both time and cost are preferable to be used, my question is how to use both?

best,

muataz

M
Mike Testro 👤 Member for 20 years 5 months

Hi Moutaz

Weightage only becomes a problem when a planned task s a combination of trades and/or location ie:

FRC Suspended slabs : 20-10-17 > 15-12-17 > 40d

When this task is spread over - say - 5 slabs then you have both a time and cost weithage problem.

This is because planners are lazy and lack pride in their profession.

It is just as easy to plan the work in detail ie:

Level 1

Slab Form > Rebar > Edge Forms > Pour Concrete

Level 2

                Slab Form > Rebar > Edge Forms > Pour Concrete

Etc

Then you just report % complete in either time or volume on each task.

Best regards

Mike T.

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Hi Moutaz,

To Calulate weightage you can do it by either

  • By Only Cost
  • By Time and Cost

If the Project is only Construction then Manhours / Activity would be good.

If the Project is Engineering, Procurement and Construction then it would be better to use Manhours / Deliverable, Cost / Item and Manhours / Activity to measure each WBS.

 

In an Overall summary ou can use Cost or the weightage given by Client.

 

Regards

Jithin

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts