NEC3 CE and programme ahead of schedule

Hi,

We have a contract where there is an accepted programme which shows the planned completion and a completion date. Due to a compensation event no 1 the planned completion and completion date has been extended by 2 days.

Due to good weather progress has been ahead of schedule on site but now another CE has raised which will effect the critical path.

As the planned completion is now 2 days ahead of schedule, ie what it was prior to CE 1, is the contractor entitled to claim the 2 days delay costs (preliminaries) that has already been implemented in CE1. In effect claiming the same 2 days twice?

If this is the case does the completion date move out by a further 2 days as well?

Many thanks

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts