scope of work

Hi All,

Few activity in the scope of work doesn't include in the b.o.q, this additional activity involve material/labour.

it is the right thing for my to request variation for the additional work from the client?

Please advise.

Regard

Ron

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ronron

It all depends on your type of contract - if it is a fixed price with no re measurement then the missing items may well be within the whole scope.

Another siuatiion could be that the items are in the spec and drawings but missing from the BoQ in which case they should be in your programme but subject to extra payment.

If they are completely new items then you should have an appropriate EoT and costs through the change / variation route in your contract.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts