Dear All,
First I am glad to join your network. It's good to know that any problem surely has an answer on this site.
I am working with Primavera P6 v7
I have an activity with many predecessors.
One of this predecessor is a completed activity but is still indicated as a driving one.
Other predecessors didn't start but are not indicated as driving.
I don't understand why. Any clue ?
Thank you
Arnaud,
Do not confuse Driving Relationship with Driving Activities. It is the predecessor logic that is determining the early start of your activity, not just the preceding activity. In all probability, you have out-of-sequence progress and some of the predecessors to your complete predecessors are still active. That is what makes scheduling so interesting! Good luck.