Electrical Works Planning
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Andrew
I am going to work on a railway project,which is altogether new to me. Can you please let me know salient features of the project like WBS,cost,Schedule for any typical work.
thanks
sridhar
James,
Unfortunatley I have never done any electrical substation work.
The questions I mentioned to you were aimed at providing you with a starting point.
These are the type of things Id ask to generate a converstation with the site manager and project engineer.
Im very sorry if I misled you in my knowledge of the subject, however my background in aeronautical engineering and railway construction.
I would suggest that if you havent already received any more hints from PP, that you post these further questions on PP and see what sort of response you get back.
Andy
Dick
Thanks for immediate reply.
Can you please let me know some more questions in this respect so that i get maximum information from site manager and prepare this schedule as per actual site requirements.
regards
James,
A very open question indeed.
What is the nature of the project work, where will it be, what do you need to acheive with these early works?
I think you just need to get an understanding from the site manager as to what will be required, is it a temporary switch box on a pole? or are you wiring temporary buildings? Do you need a substation? What needs to be powered?
Sorry mate but its a fairly open ended question.
Andy