Pharma Project - Validation

P
Peter Holroyd 👤 Member for 21 years

Davide,



we tend to use modulat test scripts which cuts down on the total number of docs needed.



Weighting - I just use the estimate manhours for that V&Q phase with individual manhour activities prorata to their durations, as generally only 1 or 2 people produce the docs



100% Credit is only given at client doc sign off so set progress plan accordingly



Rgds



Peter

D
Davide Catuzzato 👤 Member for 22 years 1 month

Peter,



I did a nice P3 network having all the link and all the right sequnce to manage and controll the V&Q schedule.

I have more difficulties to manage the progress of the protocols or report, to track them and to link them to the related P3 activities (for each level 3 activities we can have to 6 IQ/QO protocols and report).



How do you weight the protocols ? Point, Stdmhrs, nr. of page ?



Thanks



Davide

P
Peter Holroyd 👤 Member for 21 years

Davide ,



can you be more specific ?



Here the V & Q work is scheduled as part of the project work in the normal manner from DQ, IQ, OQ & PQ.

The department gets it own level 3 programme and then generally uses excel / access to create the lists / matrices required for tracking creation, approval and registering of all those documents specified in the master plan.


Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts