Recovery Schedule

A
Amro Ahmed 👤 Member for 17 years 5 months

Dear All,

What the best method to issue Recovery Schedule   using baseline and update are already exist in step

A
Amro Ahmed 👤 Member for 17 years 5 months

it,s available to  fix actual dates as baseline from Global Changes then add Remaining Works but i want to get the best detailed procedure to do that?

R
Rafael Davila 👤 Member for 22 years 3 months

If you are into trouble probably original schedule was no good. At times in order to recover you will have to re-schedule your plans with completely new logic. Let the team that will be responsible to implement it be free to make the necessary adjustments, if major surgery is required then let it be.

The fixation with Baseline Schedule some owners and delay analysts have can do more harm than good to the scheduling and managing of the job.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts