Labour Units mismatch in p6
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
This is most likely due to their conversion from days to hours being set differently than yours. Remember that P6 always calculates in hours, but can be set to show days based on a fixed conversion rate set either in the Admin Preferences or Users Preferences.
The reason that the rollups work is that the conversion to days for summaries is also impacted by the Global Default Calendar Selection.
An easy way to check is to show units in hours instead of days and see if everything is correct.
This P6 feature causes more confusion with users than just about anything else.
Ian
http://www.emerald-associates.com