PMO Training for Planners

Hello,

Some say that working in project planning and controls is super easy, so I'm wondering if anyone is looking for some hands-on PMO training?

Thanks

D
David Plyler 👤 Member for 1 month

I am still using Sure Trak scheduling software. I am having an issue where there is a 1-day activity with an FS tie. If the early start is Wednesday Sept. 5, the early finish date is September 6. The previous 1-day activities finish on the same day. All of the dates after that finish a day late. The next activity still starts on the correct day. Activities that have multiple days are also finishing a day late. Any ideas?   

Forum Sponsor

Top Posters

Christopher Ganotice
1 posts
Ola Gbotoso
0 posts
James Williams
74 posts
pennyu
0 posts
jaasland
0 posts
Doron El
3 posts
Erim INANC
2 posts
gorilpk
0 posts
Ricky
0 posts
pinoyplanner
1 posts