Hi,

I'm updating the actual progress of a project during which i put the % complete of a task as 75%. i need to reflect this 75% on the actual cost of the task, but when i enter the 75%, the actual cost is calculated to be more of a 90% of the total cost. I only loaded a prorated material resource if this matters. How do i reflect the % complete entered to a task on the actual cost ?!

Thanks,