The best solution for Progress Curves Early & late is at this site:
http://www.cla-it.eu/TMSDetails-general.html
Best regards
Create a new job file from original.
Set all tasks to as late as possible constraint.
Update project.
Verify no re-scheduled task overrides any finish no latter than constraint you previously had in the original. If so re-set those to your original finish no latter than constraint.
Update project.