Roll-up Summary in "Group By Summary"
Forum Sponsor
Top Posters
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Peter Holroyd
51 posts
fridau
0 posts
I’ve had this problem as well. It’s one of the many errors (in the bar styles section) of MSP.
If you replace "baseline start" by "start" it works. In my particular schedule all first activities under each WBS started as planned so I got away with this ’workaround’.
H.T.H.
tnx pals,
ill do some experimenting as u adviced james....
ill send email for more info jaya...
again thank u for ur time & advice...
regards
Ronaldo,
can you explain more...
If u want the project summary, u can get the same by Project summary task from the options menu...
otherwise, if u want to show summary for a set/group of activities, the same can be done adding additionjal information in the Text/number field...
for any details/clarifications contact me at [email protected]
J
Ronaldo,
I cant get it to do it either. It might be to do with having formatted the grouping AFTER having saved it with a baseline.
It could be worth performing a few experiments.
HTH.
James.