How reliable is peak unit values.?
Forum Sponsor
Top Posters
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
David Smith
4 posts
Vinod,
as you entered 16 hours on the last day, MS Project put the all 16 hours at the same time where the initial 4 hours were, the morning.
click zoom in (the magnifier +) to see the time more in details
if you want to spread the 16 hours during the whole day, enter 8 hours during the morning and 8 hours in the afternoon; ms project will display a warning saying the resource is assigned beyond the task limit on the fixed duration tasks; click OK
the resource graph will show peak unit = 2.
Alexandre