Unlink Remaining Duration & % Complete
Forum Sponsor
Top Posters
Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts
Hi Ian
The Problem with MS is
% Complete = % Time Complete
You Can use % Work Complete
Original Duration in P3 is known as baseline Duration in MS.
And Duration is Actual Duration & Remaining Duration
I Hope this Helps
Hi there, the autocost thing is in P3. Busy loading MSP at the moment, if I can find something, will reply. Wher are the MSP Fundis?
Use the Autocost Rules and untick the remaining duration & % complete.