Predecessors status on the same view

Z
Zhang Haixiang 👤 Member for 21 years 1 month

some activities may have more than one predecessor,you should think about how to sort by preducessors’ status.

I think you can save the project as Access database,then do it in ACCESS,it is more powerful than PROJECT for data processing.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Alvaro,

If you want to sort the tasks by their predecessors being completed or not, you would better export data to Excel and finish your work there.

Hasta luego

Á
Álvaro Gómez 👤 Member for 21 years

Thanks all,



my idea is to visualize the predecessors status in a column, in order to sort the tasks by this predecessors status (first 100% complete, next 0%). On this way, the user could see quickly the work which really can be started.



I am still trying different methods to solve this problem, such as macros Alexandre suggest.



Regards.



Álvaro.

R
Raj Maurya 👤 Member for 21 years 10 months

Alvaro,

Why are you not trying with Network diagram? I think that will help you to show the progress as well. Only thing you need to filter the required activity.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

I still don’t understand.

When you set a non-critical task (one with free slack or one with total slack) to 100% complete,

a) the slack remains the same until the 1st successor has started

b) once the 1st successor has started, the slack is 0 (zero)

c) I tried several times with MSP 2002 US, you cannot have a "blank" Slack field, the NULL value is ZERO.

Did you get another result?

I would be interested to know.

I could send my test file to your email address if you want.

Alexandre

P
Philip Jonker 👤 Member for 21 years 7 months

Hi, I did not say zero slack, but the slack should be blank, ie no value in the column.

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi there,



Alvaro,

MS Project does not have such a view that you wish.

It would take a macro to copy predecessor "name" and "%complete" fields in text fields on a specified task row where the resource is working on.



Philip,

MS Project slack is what makes the difference between critical and not critical tasks; I don’t understand how a slack zero would make a task being completed: what about not started or not completed critical tasks?

A task is completed if it has a actual finish date or a %complete = 100, as MSP does not distinguish actual finish and %complete.



All the best

P
Philip Jonker 👤 Member for 21 years 7 months

The normal way to see if an activity is completed, is to look at the float, or slack as referred to in MPS, I do not recall if they have this function. If the slack is blank, the activity is completed

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts