Free Slack

T
Tomasz Wiatr 👤 Member for 21 years 6 months

Option ALAP in MSP is simmilar to ZFFC in P3 so valuable for You of course. But other interesting option is setting the finish date of project (instead of traditional start date project - in MSP we have only start OR only finish...). In this case MSP assume that all tasks are ALAP automatically. Meybe this way is valuable too. If You change finish date for start date you can revert (!) it for standard ASAP schedule. It is practical way in some cases, I suppose.



Good Luck

V
Vladimir Liberzon 👤 Member for 25 years 4 months

It may be used for the initial planning. But the schedule will change during project execution and these additional constraints being artificial will influence future schedules.

R
Raj Maurya 👤 Member for 21 years 11 months

If you assign the task constraint ALAP then total slack as well as free float become zero, but if insert a column of free slack and then put another constraint FNET to make free slack zero.eg if task is showing 2 days free slack with current task finish date then you put FNET 2 days later then your free slack will become zero.

P
Paul Harris 👤 Member for 25 years 2 months

As you have correctly alluded to setting a task in MSP to ALAP consumes all Total Float and not Free Float as in Primavera software.



I have not found a solution.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au

Forum Sponsor

Top Posters

Erkan Polater
9 posts
Soheil Barekat
4 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts
Vahidazimi01
0 posts