Fixed Duration, Units, Work

G
Gerry Morgan 👤 Member for 21 years 6 months

Hi Tony

Thanks alot, I see you are in the North West of England, I am originally from Manchester, now living in Toronto, Canada.

Thanks again for the help, Gerry.

T
Tony McClennon 👤 Member for 23 years 6 months

Hi Gerry,



Glad that the info was of help.



The information was retrieved from MS Project’s own Help guide and not from their web-site (just to save you a bit of time looking!)



I typed "fixed duration" into the search facility, and it then gives you a selection of related help subjects.



Regards,



Tony

G
Gerry Morgan 👤 Member for 21 years 6 months

Hi Tony

Thanks for taking the time to reply and explain, it was a big help, I will also check out the Site.

Regards Gerry

T
Tony McClennon 👤 Member for 23 years 6 months

Hi - MSP Help has some info on this which may be of use. I have also used this to explain the differences, which I have shown below - hope this is of use to you.



Fixed Duration:

The task will remain at whatever duration value has been entered provided effort driven is turned off. If two painters assigned full time for 4 days, duration is 4 days. If additional two painters are assigned, then each painter will be assigned for 50% of their time to keep the duration the same.



Fixed Units:

The allocation (i.e. percentage) of a resource drives the resource requirement. For example, if the task is of 4 days duration and two painters are allocated full time (100%), the painters workload total will be 8 days of work. Again, provided effort driven is turned off, if an additional two painters were assigned, then the total workload would be 4 men x 4 days = 16 days of work, but the duration would remain at 4 days. However, if effort driven is turned on, the duration will be recalculated based on the additional resources assigned to 2 days.



Fixed Work:

As resource assignments are changed, MS project will recalculate the duration e.g. if two painters assigned for 4 days, then two more are assigned to the task, the task duration is reduced to 2 days i.e. the total work content of the task remains constant. Effort driven automatically turned on.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts