Could we do it or not?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Shahul
If there has been an instruction to omit an element of the work from the contract that should only reduce the contract period by way of adjustment in an EoT claim.
So in your case where there is an EoT situation the contract period can be reduced by the time allowed for the omitted work.
Dont just delete the task - turn it ito a milestone and add the word "deleted" to the discription.
Best regards
Mike Testro.
Dear Shahul,
You need to understand the overall impact and the size of the revised scope.
If the activity is cancelled, then you need to update the program of works to represent the actual work that is going to really happen.
After updating the program of works, then you can do the TIA.
With kind regards,
Samer
I assume the activity was a planned one, and not complete or in progress at the time it was removed from scope?
THanks Samer & Mike