Hi,
How can I add the column to show the remaining days for an activity to start? I assume it should be a formula Today's date minus the activity's start date. Please see the photo below;

Also, how can I hide the start/finish/duration columns' values for the summary lines? Please see photo below;

Thank you very much in advance.
Kind regards,
Yarkin
Thank you for your reply, I couldnt reflect the changes to the summary headings. Could you please show me steps if you dont mind? Also, for the time to go column, do you have any idea how to insert it?
Thank you,
Kind regards,
Yarkin
Hi Yarkin,
It looks like your view has a sort on it. If so, the setting to hide column details on a sort is within the Sort/Group Properties:
[[wysiwyg_imageupload:7468:]]
You will need to chose "Sub-heading with only name column" to get the desired view.
Thanks,
Ben @ Powerproject