Hello, Powerproject fanatics
Maybe the answer to my question is so obvious, however I was not able to find it
I want to enter the task duration in days; therfore I key in "5" for a task whose duration in "5 working days"
When I enter the duration of tasks in the spreadsheet, Powerproject always converts these 5 "days" into 5 "weeks", and displayes the value "25d" in the duration column.
Having looked everywhere in the dlalog boxes and the Online help, I cannot find my way.
Who will help me?
Thank you,
Alexandre
Hello Ben
Thank you!
Shame on me, I should have found it by myself!
Alexandre
Hi Alexandre,
On the View ribbon, you can change the default snapping unit in the drop down list:
[[wysiwyg_imageupload:7328:]]
I just tested it and it is this field that controls what happens when you just tap "5" into the duration field on the spreadsheet.
Thanks,
Ben @ Powerproject