Consumable Resources - Reports

E
Euan Rennie 👤 Member for 8 years 3 months

I have my programme fully resourced with "Consumable Resources" i.e Materials.  

I would ideally like to be able to export a spreadsheet which shows me:

  1. The quantity I have of each Consumable Resource 
  2. The % of the Consumable Resource which has been used to date based on Programme progress

Is there anyway to do this?  I can see the quantity of each Consumable Resource by going into Libary Explorer > Consumable Resources and selecting "Show All Fields."  Is there a way to export what I can see here into a spreadsheet?

I'm not sure if the software can do what I'm asking for above however it seems like something it should be able to do.  Any help would be greatly appreciated.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts