Adjust start date when schedule has logic applied to it

Hello everyone, I am a construction student using asta to build a schedule for a project I am working on. Now, I have built the entire schedule start to finish, but unfortunetly I have forgotten to add my preconstruction tasks, which, are required for my project. I established the start date (Notice to Proceed) for 10/12/2018 and proceeded with my schedule logic. I would like to have the preconstruction tasks starting on 8/27/2018 and move in logical order on the schedule. However, every time I reschedule, it moves the start date of my precon tasks up to 10/12/2018 regardless of constraints removed and changing the start date in bar chart format tab. Please let me know if anyone can help. Thank you - Austin

M
Mike Testro 👤 Member for 20 years 5 months

Hi Austin - Welcome to Planning Planet

You can also set week 1 as the works start date by right click the date zone and set the date for weeks 1.

Earlir dates will show as minus numbers.

Best regards

Mike T.

A
Andrew Willard 👤 Member for 12 years 9 months

Hi

 

File-Properties-Advanced properties -change the imposed start date.

 

Also make sure the date of the project report date is the new date you want

 

Andrew

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts